The attached XML gantt chart has a total of 4 processes. The first process requires roughly x5 the height of the other three due to 5 levels of tasks. However, when rendered all processes are forced to have the same height. Is there a setting in FusionWidgets to automatically allocate the necessary height of each Process, or set the height manually for each Process? If not, is there a work around?

 

 

 

Regards,

 

 

 

Rich Willmore

 