manikantaprasad Report post Posted May 22, 2009 is it possible to drag the task in gantt chart and move it above to change the sequence ie in the gantt chart x axis is months and y axis is data like (1000000004) and in the tasks there are 4 task called t1,t2,t3,t4 is it possible to change the sequence of the task as t2 t1 t3 t4 or any sequence by moving the tasks up and down in the gantt chart swf file so that the sequence can be changed and view will be changed . Share this post Link to post Share on other sites
saptarshi Report post Posted May 22, 2009 Hello, It is not possible to change the order of the tasks after they are rendered. Share this post Link to post Share on other sites
manikantaprasad Report post Posted June 9, 2009 will it can be accomplished if so pls tel me thanks and regards mani Share this post Link to post Share on other sites
saptarshi Report post Posted June 10, 2009 Hello, Currently, once the charts are rendered, it is not possible to change the order of the tasks by dragging, etc. Share this post Link to post Share on other sites